Westlake building permits
The 9th Edition (2026) of the Florida Building Code takes effect Dec 31, 2026: applications submitted from that day must comply with it.
Roof replacement / re-roof
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $24,000 job: about $79 planning zoning building fees 1 (PDF) · effective 2016-07-01
Window and exterior door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Design wind speed | 170 mph Vult |
Forms we fill for you
- Building permit application the town's own form
Hurricane shutters / storm panels
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Garage door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
A/C changeout (like for like)
What to submit
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Product approval (Miami-Dade NOA / Florida FL#)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $15,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| A/C unit distance to the property line | Allowed within the setbacks R-1 and R-2 single-family. A/C units may be placed in the side yard setback with no minimum distance stated (rear not addressed). Opaque visual screening from right-of-way and adjacent property required. Text as shown in Ord. 2020-12; current codified... |
Forms we fill for you
- Building permit application the town's own form
Fee for a $9,000 job: at least $75 (priced per item) planning zoning building fees 1 (PDF) · effective 2016-07-01
Water heater
What to submit
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Product approval (Miami-Dade NOA / Florida FL#)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $1,800 job: at least $75 (priced per item) planning zoning building fees 1 (PDF) · effective 2016-07-01
Fence / gate
What to submit
- Permit application County
- Survey (signed & sealed) City
- Product approval (Miami-Dade NOA / Florida FL#) City
- Proof of ownership City
Depends on your job
- HOA / condo association approval
- Pool barrier / safety feature form
- Contractor license / registration
- Construction plans / drawings
- Soil / compaction / geotech report
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Maximum fence height | 6 ft |
Forms we fill for you
- Building permit application the town's own form
Fee for a $6,000 job: about $129 planning zoning building fees 1 (PDF) · effective 2016-07-01
Shed / accessory storage structure
What to submit
- Site plan (or survey) Florida
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Product approval (Miami-Dade NOA / Florida FL#)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $7,000 job: about $256 planning zoning building fees 1 (PDF) · effective 2016-07-01
Generator / LP tank
What to submit
- Survey (signed & sealed) County
- Load / energy calculations County
- Permit application County
- Proof of ownership City
Depends on your job
- Contractor license / registration
- Construction plans / drawings
- Product approval (Miami-Dade NOA / Florida FL#)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Generator distance to the property line | Allowed within the setbacks R-1 and R-2 single-family. Allowed within the side yard setback with no minimum distance stated (rear yard not addressed). Opaque screening required: from right-of-way and adjacent property on lots with 7.5 ft side setback; from adjacent property on lots... |
Forms we fill for you
- Building permit application the town's own form
Fee for a $14,000 job: about $410 planning zoning building fees 1 (PDF) · effective 2016-07-01
Swimming pool / spa (new)
What to submit
- Construction plans / drawings Florida
- Permit application County
- Proof of ownership City
- Survey (signed & sealed) City
- Product approval (Miami-Dade NOA / Florida FL#) City
- Manufacturer specifications / cut sheets City
Depends on your job
- Pool barrier / safety feature form
- Contractor license / registration
- Soil / compaction / geotech report
- HOA / condo association approval
- Load / energy calculations
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Pool setback, side and rear | 3 ft Single-family detached: pools, screen enclosures, decks and patios 3 ft from the side, side street and rear lines; not in the front yard |
Forms we fill for you
- Building permit application the town's own form
Solar PV
What to submit
- Permit application County
- Proof of ownership City
- Construction plans / drawings City
- Survey (signed & sealed) (or site plan) City
- Load / energy calculations City
Depends on your job
- Photos
- Contractor license / registration
- Product approval (Miami-Dade NOA / Florida FL#)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Driveway / pavers / walkway / approach
What to submit
- Site plan (or survey) Florida
- Permit application County
- Proof of ownership City
Depends on your job
- Encroachment / hold-harmless agreement
- Lot coverage / impervious area calculation
- Survey (signed & sealed)
- Product approval (Miami-Dade NOA / Florida FL#)
- Contractor license / registration
- Construction plans / drawings
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Interior remodel / alteration (incl kitchen/bath/flooring)
What to submit
- Permit application County
- Proof of ownership City
Depends on your job
- Construction plans / drawings
- Contractor license / registration
- Survey (signed & sealed)
- Product approval (Miami-Dade NOA / Florida FL#)
- Soil / compaction / geotech report
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Uploading files
- Plans should ONLY be Submitted as .PDF files. digital submittal guidelines 11.28.23 (PDF)
- Maximum PDF File Size: (40 MBs) – Note: Use 1 of 2 & 2 of 2 to separate files if too large. digital submittal guidelines 11.28.23 (PDF)
- PDFs must be flattened. digital submittal guidelines 11.28.23 (PDF)
- PDFs MUST allow Markups. (Not be locked to disallow) digital submittal guidelines 11.28.23 (PDF)
- Example: (123M Revised Site Plan) 123 = Lot # (or last 3 of PCN #) M = Letter Code of Development See list below at end of page digital submittal guidelines 11.28.23 (PDF)
- Applicants should submit one (1) file per submittal requirement. This makes it much easier to track corrections, markups and resubmittals. digital submittal guidelines 11.28.23 (PDF)
- A digital (.pdf) copy of the completed application, plans, surveys, and all supporting documents must be submitted to https://cityviewportal.westlakegov.com/. bpr building permit application requirements rev 11.21.23 (PDF)
Built from the building department's own checklists, forms and fee schedules, the county rules and Florida law. Rules change: confirm with the building department before you submit.