Unincorporated Miami-Dade County building permits
The 9th Edition (2026) of the Florida Building Code takes effect Dec 31, 2026: applications submitted from that day must comply with it. Product approvals: Miami-Dade applies an NOA whose drawings name a code edition only to permits under that edition, so applications from Dec 31, 2026 need NOA revisions approved for the 9th Edition. From Jan 1, 2027 every underlayment under roof tile needs its own NOA (the yellow-stripe prescriptive option ends), and hip and ridge shingles need an NOA showing the UL 2375 test or the prescriptive cement attachment (Miami-Dade Product Control notices of July 31, 2026). Upload each NOA as downloaded from Product Control: its own pages and every stamped drawing sheet.
Roof replacement / re-roof
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application City
- Roofing permit application (uniform roofing form) County
- Roof fire classification listing County
- Secondary water barrier / re-nailing affidavit County
Depends on your job
- Proof of ownership
- Contractor license / registration
- Construction plans / drawings
- Roof wind uplift calculations (RAS 127 / RAS 128 or engineer's)
- Owner's Notification for Roofing Considerations (FBC 1524)
- Roof-to-wall / hurricane mitigation affidavit
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- HVHZ Uniform Roofing Application required with every re-roof in the High-Velocity Hurricane Zone
Fee for a $24,000 job: about $1,012 memo for revised building fee ordinance (PDF) · effective June 30, 2025
Window and exterior door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application City
Depends on your job
- Proof of ownership
- Contractor license / registration
- Construction plans / drawings
- Special inspector form
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $18,000 job: about $380 memo for revised building fee ordinance (PDF) · effective June 30, 2025
Hurricane shutters / storm panels
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application City
Depends on your job
- Proof of ownership
- Contractor license / registration
- Construction plans / drawings
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $8,000 job: about $374 memo for revised building fee ordinance (PDF) · effective June 30, 2025
Garage door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application City
- Construction plans / drawings City
Depends on your job
- Proof of ownership
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $4,500 job: about $373 memo for revised building fee ordinance (PDF) · effective June 30, 2025
A/C changeout (like for like)
What to submit
- Permit application City
Depends on your job
- Proof of ownership
- Contractor license / registration
- Construction plans / drawings
- Equipment tie-down / anchoring detail (or product approval / wind load calculations)
When the job value is over $15,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $9,000 job: about $218 mechanical fee (PDF) · effective form rev. 10/26
Water heater
What to submit
- Permit application City
Depends on your job
- Proof of ownership
- Contractor license / registration
- Construction plans / drawings
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $1,800 job: at least $234 (priced per item) plumbing gas fee (PDF) · effective form rev. 10/26
Fence / gate
What to submit
- Site plan (or survey) Florida
- Permit application County
Depends on your job
- Construction plans / drawings
- HOA / condo association approval
- Proof of ownership
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Maximum fence height | 6 ft |
| Maximum fence height, front yard | 6 ft |
Fee for a $6,000 job: about $231 memo for revised building fee ordinance (PDF) · effective June 30, 2025
Shed / accessory storage structure
What to submit
- Site plan (or survey) Florida
- Permit application City
- Product approval (Miami-Dade NOA / Florida FL#) (or construction plans / drawings) County
- Survey (signed & sealed) (or site plan) County
Depends on your job
- Proof of ownership
- Contractor license / registration
- Construction plans / drawings
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Maximum shed area | 400 sq ft |
| Shed setback, side and rear | 5 ft Single-family (RU-1 etc.). *Rear and interior side may be reduced to 2 ft with an affidavit of consent from the abutting owner. Sheds over 100 sq ft follow Sec. 33-50 accessory building setbacks; the RU-1 page lists rear 5 ft and interior side 10% of lot... |
| Maximum shed area inside the house setbacks | 100 sq ft The reduced shed setbacks (5 ft rear and interior side, or 2 ft with the abutting neighbor's consent affidavit) apply to sheds up to 100 sq ft and 10 ft tall; larger sheds meet the accessory building setbacks of Sec. 33-50. One shed per lot, up to 400 sq ft. |
| Maximum shed height inside the house setbacks | 10 ft |
| Shed distance from the house | 10 ft Applies to sheds and pergolas up to 100 sq ft and 10 ft high (the common case). Spacing for larger sheds is governed by Sec. 33-50 and was not verified. |
Fee for a $7,000 job: about $374 memo for revised building fee ordinance (PDF) · effective June 30, 2025
Generator / LP tank
What to submit
- Site plan (or survey) Florida
- Permit application City
- Construction plans / drawings City
Depends on your job
- Proof of ownership
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Generator distance to the property line | 3 ft to 5 ft EU, AU and GU districts. By zoning district: RU-1 3 ftRU-1M(a)=3; RU-1M(b)=3; RU-1Z=3; RU-2=3; RU-TH=3; EU-1=5; EU-1C=5; EU-2=5; EU-M=5; EU-S=5; AU=5; GU=5 |
| Generator distance to the rear line | 5 ft Rear 5 ft. |
| Screening around the generator | Required (wall, fence or hedge) From view, by a wall or hedge |
Fee for a $14,000 job: about $221 electrical fee (PDF) · effective form rev. 10/26
Swimming pool / spa (new)
What to submit
- Construction plans / drawings Florida
- Site plan (or survey) Florida
- Permit application City
- Pool barrier / safety feature form County
Depends on your job
- Proof of ownership
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Pool setback, side and rear | 7.5 ft |
Fee for a $60,000 job: about $1,263 electrical fee (PDF) · effective June 30, 2025
Solar PV
What to submit
- Permit application City
- Construction plans / drawings City
Depends on your job
- Proof of ownership
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $28,000 job: about $494 electrical fee (PDF) · effective form rev. 10/26
Driveway / pavers / walkway / approach
What to submit
- Survey (signed & sealed) Florida
- Permit application City
- Construction plans / drawings City
- Photos City
Depends on your job
- Encroachment / hold-harmless agreement
- Lot coverage / impervious area calculation
- Product approval (Miami-Dade NOA / Florida FL#)
- Proof of ownership
- Contractor license / registration
- HOA / condo association approval
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $9,000 job: about $763 memo for revised building fee ordinance (PDF) · effective June 30, 2025
Interior remodel / alteration (incl kitchen/bath/flooring)
What to submit
- Construction plans / drawings Florida
- Permit application City
Depends on your job
- Proof of ownership
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Fee for a $25,000 job: about $1,013 memo for revised building fee ordinance (PDF) · effective June 30, 2025
Uploading files
- All drawings and supporting documents in the plan package must be in PDF format plans processing guidelines (web page)
- Plan must be submitted as one PDF per plan sheet; Calculations, NOAs, Application, and Supporting Documents can be submitted as multiple page PDFs plans processing guidelines (web page)
- Calculations shall be grouped in one PDF, with pages numbered and scanned in consecutive order with cover page as first page plans processing guidelines (web page)
- All pages belonging to one NOA or one Florida approval shall be grouped in one PDF, cover pages and installation details pages together in one PDF, no isolated pages shall can be submitted. Prepare one PDF for each NOA or Florida Approval plans processing guidelines (web page)
- PDF files must have only one layer (flattened) without any embedded objects plans processing guidelines (web page)
- PDF files cannot be encrypted, or password protected plans processing guidelines (web page)
- Documents should be scanned at no greater than 300 dpi plans processing guidelines (web page)
- File names cannot contain any leading or trailing spaces File names cannot contain special characters such as: parenthesis “( )”; double periods “..”; question marks “?”; etc. plans processing guidelines (web page)
- Each file must contain the discipline code as the first letter of the file name, followed by a numerical field that closely corresponds to the sheet sequence number. plans processing guidelines (web page)
- Supporting documents shall be accepted only in 8½”x11” page size plans processing guidelines (web page)
- Plan pages shall be accepted only in sizes: 8½" x 14” 11" x 17” 12" x 18” 24" x 36” 36" x 48” plans processing guidelines (web page)
- Once the permit PDF documents are created, they should all be labeled in the following ways to help expedite the review and permitting process. plans processing guidelines (web page)
- Drawings: Each sheet should be a separate PDF file. Each sheet must be signed and sealed by the Delegated Engineer and must contain the approval stamp from the Architect/Engineer of Record plans processing guidelines (web page)
- Calculations: Must be submitted as a single PDF, and only the cover/index page needs to be signed and sealed by the Delegated Engineer and must contain the approval stamp from the Architect/Engineer of Record plans processing guidelines (web page)
Built from the building department's own checklists, forms and fee schedules, the county rules and Florida law. Rules change: confirm with the building department before you submit.