Weston building permits
The 9th Edition (2026) of the Florida Building Code takes effect Dec 31, 2026: applications submitted from that day must comply with it. Product approvals: Miami-Dade applies an NOA whose drawings name a code edition only to permits under that edition, so applications from Dec 31, 2026 need NOA revisions approved for the 9th Edition. From Jan 1, 2027 every underlayment under roof tile needs its own NOA (the yellow-stripe prescriptive option ends), and hip and ridge shingles need an NOA showing the UL 2375 test or the prescriptive cement attachment (Miami-Dade Product Control notices of July 31, 2026). Upload each NOA as downloaded from Product Control: its own pages and every stamped drawing sheet.
Roof replacement / re-roof
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Roofing permit application (uniform roofing form) County
- Rooftop equipment affidavit (BORA Policy 22-03) County
- Asbestos survey / notice County
- Roof fire classification listing County
- Owner's Notification for Roofing Considerations (FBC 1524) City
Depends on your job
- Roof-to-wall / hurricane mitigation affidavit
- HOA / condo association approval
- Signed contract / cost estimate
- Contractor license / registration
- Construction plans / drawings
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
- HVHZ Uniform Roofing Application required with every re-roof in the High-Velocity Hurricane Zone
- Mandatory Countywide Rooftop Mounted Equipment Affidavit (BORA Policy 22-03) filed with every re-roof: tick the equipment on the roof (or none) and sign
Fee for a $24,000 job: about $697 town document (PDF) · effective October 1, 2026
Window and exterior door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Window / door opening schedule County
- Construction plans / drawings County
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Site-specific design pressures above a mean roof height of | 30 ft |
Forms we fill for you
- Building permit application the town's own form
Fee for a $18,000 job: about $600 town document (PDF) · effective October 1, 2026
Hurricane shutters / storm panels
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Construction plans / drawings City
- Window / door opening schedule City
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
- Wind load calculations (design pressures)
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $8,000 job: about $438 town document (PDF) · effective October 1, 2026
Garage door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Construction plans / drawings City
- Window / door opening schedule City
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
- Wind load calculations (design pressures)
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $4,500 job: about $382 town document (PDF) · effective October 1, 2026
A/C changeout (like for like)
What to submit
- Permit application County
- A/C replacement data form County
- AHRI certificate County
- Equipment tie-down / anchoring detail (or product approval) City
- Survey (signed & sealed) City
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Construction plans / drawings
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $15,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| A/C unit distance to the side line | 0 ft to 5 ft Mechanical equipment, including A/C units and pool equipment, may project up to 60 in from the wall into a required yard (124.47(B)(1)), so the minimum is the district setback less 5 ft. Interior side yards: R1 and R2 5 ft, R3 and R4 7.5 ft (R4 lots under... |
| A/C unit distance to the rear line | 5 ft to 10 ft Mechanical equipment, including A/C units and pool equipment, may project up to 60 in from the wall into a required yard (124.47(B)(1)), so the minimum is the district setback less 5 ft. Rear yards: R1 10 ft, all other single-family districts 15 ft. By... |
Forms we fill for you
- Building permit application the town's own form
Fee for a $9,000 job: about $542 town document (PDF) · effective October 1, 2026
Water heater
What to submit
- Permit application County
- Water heater replacement data form County
- Manufacturer specifications / cut sheets City
Depends on your job
- AHRI certificate
- Signed contract / cost estimate
- Contractor license / registration
- Construction plans / drawings
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $1,800 job: about $540 town document (PDF) · effective October 1, 2026
Fence / gate
What to submit
- Site plan (or survey) Florida
- Permit application County
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Construction plans / drawings
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Maximum fence height | 6 ft 8 ft abutting non-residential |
Forms we fill for you
- Building permit application the town's own form
Fee for a $6,000 job: about $541 town document (PDF) · effective October 1, 2026
Shed / accessory storage structure
What to submit
- Permit application County
- Construction plans / drawings City
- Lot coverage / impervious area calculation City
- Product approval (Miami-Dade NOA / Florida FL#) City
- Survey (signed & sealed) City
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Shed setback, side and rear | 0 ft to 5 ft Accessory buildings take the principal building's setbacks (table 124.47(A)), but on the rear half of an interior lot behind the house the side and rear setbacks may be reduced to 5 ft (124.47(B)(3)(a)). Smallest: RZ zero-lot-line lots, 0 ft on the zero... |
Forms we fill for you
- Building permit application the town's own form
Fee for a $7,000 job: about $422 town document (PDF) · effective October 1, 2026
Generator / LP tank
What to submit
- Permit application County
- Construction plans / drawings (or manufacturer specifications / cut sheets) City
- Load / energy calculations City
- Equipment tie-down / anchoring detail (or product approval) City
- Survey (signed & sealed) City
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Generator distance to the property line | 2.5 ft Generators may encroach up to 50% of the required side or rear setback (R1/R2 side setback 5 ft -> 2.5 ft; smallest stored); not within 5 ft of the front plane of the house; A/C may project up to 60 in from the building wall |
Forms we fill for you
- Building permit application the town's own form
Fee for a $14,000 job: about $535 town document (PDF) · effective October 1, 2026
Swimming pool / spa (new)
What to submit
- Construction plans / drawings Florida
- Permit application County
- Survey (signed & sealed) City
- Lot coverage / impervious area calculation City
- Pool barrier / safety feature form City
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Pool setback, side and rear | 5 ft Single-family pools: setbacks in required side or rear yards may be reduced to 5 ft (no encroachment onto a recorded easement); measured from the outer edge of the pool deck (fenced pools) or the exterior of the screen enclosure. |
Forms we fill for you
- Building permit application the town's own form
Fee for a $60,000 job: about $1,542 town document (PDF) · effective October 1, 2026
Solar PV
What to submit
- Permit application County
- Construction plans / drawings City
- Special inspector form City
- Survey (signed & sealed) City
Depends on your job
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $28,000 job: about $762 town document (PDF) · effective October 1, 2026
Driveway / pavers / walkway / approach
What to submit
- Lot coverage / impervious area calculation Florida
- Survey (signed & sealed) Florida
- Permit application County
- Contractor license / registration City
Depends on your job
- Encroachment / hold-harmless agreement
- Product approval (Miami-Dade NOA / Florida FL#)
- Signed contract / cost estimate
- Construction plans / drawings
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $9,000 job: about $455 town document (PDF) · effective October 1, 2026
Interior remodel / alteration (incl kitchen/bath/flooring)
What to submit
- Permit application County
Depends on your job
- Construction plans / drawings
- Signed contract / cost estimate
- Contractor license / registration
- Encroachment / hold-harmless agreement
- Insurance certificate
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $25,000 job: about $714 town document (PDF) · effective October 1, 2026
Uploading files
- Document names must comply with the Document/File Naming Convention*. how to apply for a permit (web page)
- All files need to be in Adobe Acrobat PDF format. town document (PDF)
- The following naming conventions should be used when uploading documents online for building permit submittals. town document (PDF)
- Notice of Commencement NOC Owner/Builder Affidavit OB Power of Attorney POA town document (PDF)
- Product Approvals Product Approval (One file for all PA’s) town document (PDF)
- Each sheet within a plan set must be bookmarked, and each plan bookmark should include the prefix of the trade (A for architectural, M for mechanical, etc.) followed by the sheet number and sheet name town document (PDF)
Built from the building department's own checklists, forms and fee schedules, the county rules and Florida law. Rules change: confirm with the building department before you submit.