Parkland building permits
The 9th Edition (2026) of the Florida Building Code takes effect Dec 31, 2026: applications submitted from that day must comply with it. Product approvals: Miami-Dade applies an NOA whose drawings name a code edition only to permits under that edition, so applications from Dec 31, 2026 need NOA revisions approved for the 9th Edition. From Jan 1, 2027 every underlayment under roof tile needs its own NOA (the yellow-stripe prescriptive option ends), and hip and ridge shingles need an NOA showing the UL 2375 test or the prescriptive cement attachment (Miami-Dade Product Control notices of July 31, 2026). Upload each NOA as downloaded from Product Control: its own pages and every stamped drawing sheet.
Roof replacement / re-roof
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Roofing permit application (uniform roofing form) County
- Rooftop equipment affidavit (BORA Policy 22-03) County
- Asbestos survey / notice County
- Roof fire classification listing County
- Owner's Notification for Roofing Considerations (FBC 1524) City
- Secondary water barrier / re-nailing affidavit City
Depends on your job
- Roof-to-wall / hurricane mitigation affidavit
- HOA / condo association approval
- Insurance certificate
- Contractor license / registration
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
- HVHZ Uniform Roofing Application required with every re-roof in the High-Velocity Hurricane Zone
- Mandatory Countywide Rooftop Mounted Equipment Affidavit (BORA Policy 22-03) filed with every re-roof: tick the equipment on the roof (or none) and sign
Fee for a $24,000 job: about $651 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Window and exterior door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
- Window / door opening schedule County
Depends on your job
- Construction plans / drawings
- Insurance certificate
- Contractor license / registration
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Site-specific design pressures above a mean roof height of | 20 ft |
Forms we fill for you
- Building permit application the town's own form
Fee for a $18,000 job: about $489 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Hurricane shutters / storm panels
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
Depends on your job
- Insurance certificate
- Contractor license / registration
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
- Construction plans / drawings
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $8,000 job: about $220 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Garage door replacement
What to submit
- Product approval (Miami-Dade NOA / Florida FL#) Florida
- Permit application County
Depends on your job
- Insurance certificate
- Contractor license / registration
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $4,500 job: about $123 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
A/C changeout (like for like)
What to submit
- Permit application County
- A/C replacement data form County
- AHRI certificate County
- Equipment tie-down / anchoring detail City
Depends on your job
- Insurance certificate
- Contractor license / registration
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
- Construction plans / drawings (or product approval)
When the job value is over $15,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| A/C unit distance to the property line | 3 ft |
Forms we fill for you
- Building permit application the town's own form
Water heater
What to submit
- Permit application County
- Water heater replacement data form County
Depends on your job
- AHRI certificate
- Insurance certificate
- Contractor license / registration
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fence / gate
What to submit
- Permit application County
- Survey (signed & sealed) City
Depends on your job
- HOA / condo association approval
- Encroachment / hold-harmless agreement
- Product approval (Miami-Dade NOA / Florida FL#)
- Construction plans / drawings
- Insurance certificate
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Maximum fence height, side and rear | 6 ft Residential side/rear yards |
| Maximum fence height, front yard | 4 ft Residential front yard |
Forms we fill for you
- Building permit application the town's own form
Fee for a $6,000 job: about $379 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Shed / accessory storage structure
What to submit
- Permit application County
- Survey (signed & sealed) City
Depends on your job
- Insurance certificate
- Contractor license / registration
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Maximum shed height | 25 ft Accessory buildings and structures: not over two stories or 25 ft; they must also meet the district setbacks (Table 10-2, not in the online code). |
| Shed distance from the house | 10 ft Accessory building at least 10 ft from a principal structure and not blocking emergency access to it. |
Forms we fill for you
- Building permit application the town's own form
Fee for a $7,000 job: about $296 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Generator / LP tank
What to submit
- Permit application County
- Survey (signed & sealed) City
- Construction plans / drawings City
Depends on your job
- Insurance certificate
- Contractor license / registration
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Generator distance to the property line | 3 ft |
Forms we fill for you
- Building permit application the town's own form
Fee for a $14,000 job: about $484 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Swimming pool / spa (new)
What to submit
- Construction plans / drawings Florida
- Permit application County
- Survey (signed & sealed) City
- Pool barrier / safety feature form City
Depends on your job
- Special inspector form
- Insurance certificate
- Contractor license / registration
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Limits
| Pool setback, side and rear | 5 ft to 20 ft Measured from the inner edge of the waterline (screen enclosures and decks: their outer edge). Smallest: BCRM-5 5 ft; RS-6 8 ft; RS-2 to RS-4 10 ft; RS-1 and agricultural/estate 20 ft. By zoning district: A-1 20 ft, BCA-1 20 ft, AE-1 20 ft, AE-2 20 ft,... |
| Minimum pool barrier height | 48 in |
Forms we fill for you
- Building permit application the town's own form
Fee for a $60,000 job: about $1,709 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Solar PV
What to submit
- Permit application County
- Survey (signed & sealed) (or site plan) City
- Construction plans / drawings City
- Manufacturer specifications / cut sheets City
Depends on your job
- Insurance certificate
- Contractor license / registration
- Encroachment / hold-harmless agreement
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $28,000 job: about $861 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Driveway / pavers / walkway / approach
What to submit
- Survey (signed & sealed) Florida
- Permit application County
Depends on your job
- Encroachment / hold-harmless agreement
- Lot coverage / impervious area calculation
- Product approval (Miami-Dade NOA / Florida FL#)
- Insurance certificate
- Contractor license / registration
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $9,000 job: about $350 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Interior remodel / alteration (incl kitchen/bath/flooring)
What to submit
- Construction plans / drawings Florida
- Permit application County
- Asbestos survey / notice City
Depends on your job
- Insurance certificate
- Contractor license / registration
- Survey (signed & sealed)
- Encroachment / hold-harmless agreement
- Load / energy calculations
- Manufacturer specifications / cut sheets
- Product approval (Miami-Dade NOA / Florida FL#)
When the job value is over $5,000, a Notice of Commencement must be recorded, posted at the job and a copy filed with the building department before the first inspection (F.S. 713.135).
Forms we fill for you
- Building permit application the town's own form
Fee for a $25,000 job: about $780 City of Parkland Building Department JULY 1 2026 FEE SCHEDULE HB 803 (PDF) · effective July 1, 2026
Built from the building department's own checklists, forms and fee schedules, the county rules and Florida law. Rules change: confirm with the building department before you submit.